I think I don't know how to use this option "Auto update of left work on Pool" of global parameters (timesheet)
Even if a ressource of the pool enter real work with no left work, the left work of the pool is not automatically updated, it stays equal to the initial assigned work.
How can I achieve that the left work of the pool is set to 35.47 days in the attached image
Hello, is your resource part of your pool?
I find it strange that your resource is on top of your pool.
What version are you on?
The option you indicate allows the remaining work in the pool to be decremented automatically when a resource (in the pool) no longer has any remaining work to do.
See this :
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.