But on 10th Aprilm I came to know that the materials will be available on 16th April. I dont want to change the duration at that point of time, because I want to compare the actuals with baseline dates. Further since there is no resource assigned, timesheet cannot be used to enter the actuals.
Your question is how to update the progress of this activity. OK.
So my question is how do you do to follow the progress before this modification of date ?
In fact, it seems difficult to calculate a progress without data workload. Alternatively, you can continue to use a rule of three to personally assess the progress calculated over different timescales.
Perhaps I don't fully understand your concerns so my answer at this point is : The progress depends on your own calculation then written down into a textual area.
Otherwise, use the functionnality "BASELINE" to keep a photo of your project with this activity you can compare later with your current Gantt.
Best regards
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.