Hello,
I'd like to be able to send an event notification when the remaining workload changes. This will alert the project manager of any potential deviations and, if necessary, require validation.
How can this be achieved?
I guess you don't want an alerts on remaining workload changes, but on revised workload changes.
Left work (remaining workload) changes every time someone enters real work, so this is very (yes very very) often.
So I think you are interesting on reevaluation of left work that changes the total work (real + left = revised)
There is no alert on all changes.
All you have is an indicator on revised compared to assigned (or compared to validated)
If you use revised compared to assigned and set alert at 110%, you'll get a message when revised = 110% of assigned.
So if you set the indicator at 101%, you'll get an alert when resised is over assigned (of 1%).
But you'll get the alert only once, not on all changes.
You can just set to values : warning (for instance at 1% to highlight any increase) and alert (for instance à 20% when over use becomes unbearable.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.