It miss a lot of informations:
Did you link children and parent? Do you work with workload or only with declarative information entered manually the progress? This is normal in this case, the tool does not perform automatic aggregations on manual filling without steering by workload left and done, you have to keep on filling the progress of the parent manually. About workflow if an option is enabled in global parameters, parent can be steered by children's status.
For the little I can see, you don't have work-driven planning.
So progress is not based on real work input.
Only solution to get consolidated progress is use "manual progress" for fixed duration tasks.
Then you have to indicate the weight (or the way the weight is calculated, for instance from validated work) of each tasks.
If a project has 2 tasks, one is at 100% and the other at 0%, what is the progress or the project ?
No it is not 50%. It can be 50% only if tasks have same weight in the project.
If first is DEV and second is TEST, DEV may represent 80% of the project, TEST only 20%.
That why we advise to use Work Driven planning.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.