Critical resources explained

More
28 Nov 2025 16:56 #1 by tonix
We are having problems understanding critical resource list, that we show in attached picture (resource names have been deleted).

The table is clear if we exclude "overbook mode" and "including overused" columns.

Doubts:
"overbook mode" and "including overused" seems to be misleading or inverted: from manuals it looks like overbooked is the sum of normal and overbooked, and including overused seems to be the difference, but we ask why not to use more precise words, and why use different words (overbooked and overused).
Any way you want to call them, the three planned columns dont' match.

Margin column seems to be the difference from normal mode and available time, while we feel it should be the difference among (normal + overused) and available (unless making a double raport, one related to normal mode and one related to total work).

As final conclusion, we are in confusion.

What are we missing?
 
Attachments:

Please Log in or Create an account to join the conversation.

More
02 Dec 2025 11:41 #2 by maxca
Replied by maxca on topic Critical resources explained
Hello,
The table shows the number of days available for resources during this period.
The number of days planned for this resource in the schedule for this resource.
The overbooked mode indicates the number that would be required to complete the task.
The number of overuse indicates that the end date is too short and that this number of overuse would be required to finish on time.

Have a nice day,
The following user(s) said Thank You: tonix

Please Log in or Create an account to join the conversation.

More
12 Dec 2025 15:42 #3 by babynus

What are we missing?

Possibly a training course ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
12 Dec 2025 17:50 - 12 Dec 2025 17:52 #4 by tonix
Replied by tonix on topic Critical resources explained

Possibly a training course ?

Or just a better manual.
Last edit: 12 Dec 2025 17:52 by tonix.

Please Log in or Create an account to join the conversation.

More
12 Dec 2025 17:59 #5 by babynus
Very good idea : we will concentrate 1 resource for about 1 year to build a much more comprehensive manual and then ... nothing.

Please read the AGPL Licence.
You already use a free sofware, and we owe you nothing, not even a working software.

It is end of week, I really I get angry about users who don't give a peny and request to have the moon for nothing.

And just one more remark : what you expect is the user manual that we provide during Project Leader training course.
But we don't give it for free.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
12 Dec 2025 19:20 #6 by tonix
Replied by tonix on topic Critical resources explained
It's a question we already had some years ago and I don't want to waste time on that again.
I'm introducing Projeqtor in other organizations and proposing them to pay your yearly subscription, so I don't feel like abusing this software.
On the other side, I feel that some efforts on using better terms or explaining concepts differing from normal usage would improve Projeqtor usability.
Thanks for all.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.046 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.