I am actually working on a project A which is planned for 15 days (01/04/2012 till 15/04/2012) and all activities have been recorded on the application. After 5 days (05/04/2012), I have another activity (duration = 1 day) from a project B which has higher priority than project A and need to be input on the 6th day (06/05/2012) of project A’s planning.
This delayed the planning of project A by 1 day and will normally finished on the 16th day (16/04/2012), which means that all tasks from project A as from the 6th day (06/04/2012) should be delayed by 1 day.
Is there a way to move all projects from the 6th day (06/04/2012) by 1 day? (i.e. move all activities on the 06/04/2012 for project A to 07/04/2012, and so on)
Or this should be done manually on all activities?
You should succeed this way :
- define a fuixed milestone for start of project B (05/04)
- link this mlilestone to project B
- set priority of activity on project B very Low (10)
- run planning for both projects.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.