18 Jun 2012 11:27 #1 by Benoit
Hello Everybody,

I would like to know, if it's possible to creat automaticly some activity when you creat a new project.

I try to explain, when I creat some new project, i creat alway the same activity in this project, is it possible to automatize this manipulation, please ?

A small other question is about hour report, is it possible to use "." and not a ",", please ?

Thank you for your help

Best regards,

Benoit

Please Log in or Create an account to join the conversation.

More
18 Jun 2012 12:22 #2 by ThierrC49
Hello,

You can make a model of plan, then you could past the planning template at start of your project.

Thierry,
The following user(s) said Thank You: Benoit

Please Log in or Create an account to join the conversation.

More
18 Jun 2012 13:48 #3 by babynus
Hi,

What you need exists : define a template project, with activities you need (you can also define links between activities).

Then, just create your new project by copying the template !

The "template" project type exists for this mean : any project leader can copy it !

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: Benoit

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.029 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.