Hello,
I have a particular project to modelize. Here I have two parallel activities which don't have the same ressource. They begin at the same time, however the second activity (which have a lower workload than the first) cannot finish before the first as they are conducted parallely. How can I give this condition to Project'Or RIA?
Thanks in advance.
You may try one or many hints amongst :
- add a milestone to fix the start
- play with priorities
- adapt assignement rate so that second task lasts longer than work
- play with planning mode : maybe fixed duration would be better for second task
- try a end-start constraint with a negative delay between tasks
- think about your problem in a new way : maybe these particuliar contraints are due to incorrect split of tasks, maybe it should be one only task, maybe there should be 3 or more tasks
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.