11 Oct 2012 11:37 #1 by ekolossov
Can you please explain how Ticket and Planning Activity (on Ticket) suppose to work?
I would expect that when activity status changed, the status of ticket changed as well but it not working that way.
If we set activity originated from ticket it not doing that as well.
Regards,
Evgueni

Please Log in or Create an account to join the conversation.

More
11 Oct 2012 23:51 #2 by babynus
Hi,
It is mostly used for maintenance task : you have a Planning activity on wich you know you'll have to spend X days on a given period : you plan this activity, assigning resources (and then you'll be sure they will have some time left to work on this task).
When entering real work on a ticket, work will be added to the "Planning activity" work, and left work on planning activity will be decreased.

There is not link between item status.
Globally, there is no automatic mecanism that changes status of an item from another one.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
12 Oct 2012 08:34 #3 by ekolossov
"When entering real work on a ticket, work will be added to the "Planning activity" work, and left work on planning activity will be decreased." - I understand it is not working other way around? So, it is not updated on ticket when you will put hours into Real Work Allocation?
Looking not extremely useful because people actually need to update both of them!
I think at least it should link status.
If you consider the whole set: Ticket->Requirements->Task then you need to update status in 3 places for the same work!
Regards,
Evgueni

Please Log in or Create an account to join the conversation.

More
13 Oct 2012 12:33 #4 by babynus

So, it is not updated on ticket when you will put hours into Real Work Allocation?

No, it is not possible : several tickets can be linked to same planning activity.

Looking not extremely useful because people actually need to update both of them!

They just have to update ticket (as they work on Ticket). It will automatically update planning activity work.

I think at least it should link status.

No, it is not a bijective link.

If you consider the whole set: Ticket->Requirements->Task then you need to update status in 3 places for the same work!

Yes, but it's not the same point of view, and it's not 1 to 1 bijective link : A ticket can point to several Requirement and requirement can point to several tickets...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.