23 Jan 2013 11:45 #1 by JCDe
Questions was created by JCDe
Question about ticket
When entering the work on the tickets, the calculation of hours to the assignment can create an error if you consume more than one day: All times are reported on the same day and thus create an error

When creating a ticket is obliged to register to add a piece attached. Possible to to add a piece attachment before saving?

stop script
Is it possible to stop scripts loading? ex schedule

Risks & acttion
Risks or actions can not be shared by teams or clients.
Is it possible to define rights a function of a type of risk or action?

Please Log in or Create an account to join the conversation.

More
24 Jan 2013 09:37 - 24 Jan 2013 09:38 #2 by babynus
Replied by babynus on topic Re: Questions

When entering the work on the tickets, the calculation of hours to the assignment can create an error if you consume more than one day: All times are reported on the same day and thus create an error

It is not really an error : it is just an overload of work on a given day. The error is to enter several days of wrok in one time : best practice is always to enter wxork day by day (so work entered one day will not be more the resource capacity). In this case, the error in behind the keyboard :evil:

When creating a ticket is obliged to register to add a piece attached. Possible to to add a piece attachment before saving?

Already requested (Ticket #61). It may be really usefull but implies to reconsider complete tool framework. Will not be high priority.

stop script
Is it possible to stop scripts loading? ex schedule

No it is not possible.

Risks & acttion
Risks or actions can not be shared by teams or clients.

Yes they can.

Is it possible to define rights a function of a type of risk or action?

No, it's not possible to define visibility depending on type of risk or action. Visibility is always base on Project. What you may do is define specific sub-projects : one for client visivility, one for private team visibility. Team can then be affected to top project, to see both. Client is only affected to sub-project get s limited visibility.

Babynus
Administrator of ProjeQtOr web site
Last edit: 24 Jan 2013 09:38 by babynus.

Please Log in or Create an account to join the conversation.

More
24 Jan 2013 22:21 #3 by JCDe
Replied by JCDe on topic Re: Questions
you're right I had not thought about the external project solution
Tanks for your support ;)

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.