ProjeQtOr free project management software - Activities plannification "ASAP" vs "Regular btw dates" - ProjeQtOr
 
 

Activities plannification "ASAP" vs "Regular btw dates"

More
25 Jan 2013 11:09 #1 by GilP
Hello,
I created two activities, both assigned to the same resource. Rate of the resource is 100%. One activity is on the whole year, regular between dates, priority 500. The other one is urgent (I used asap and priority 1). I would like the resource to work only on the urgent activity before to go back on the "regular between dates" activity. How could I do that? The plannification keeps the "regular between dates" activity in parallel with the "as soon as possible" one.

Many thanks,
Best regards,
Gilles

Please Log in or Create an account to join the conversation.

More
25 Jan 2013 13:29 #2 by babynus
Hi,

Have a look at the planning calculation mode in the online manual (planning 3/5).
You'll better understand how planning is calculated, and then have it fit your needs.

The easyest way to get what you expect is to define the urgent activity as a predecessor of the reglar activity...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.