problem planning

More
29 Jan 2013 19:28 #1 by JCDe
problem planning was created by JCDe
Hi,

I have a problem planning.
See my document attach for the graph

Problem 1
I have 4 spots with such constraints: Regular between 2 date.
Each to the same resource

I calculate manually the delay to check the workload

My workload shift 1d ... It's strange? It does not calculate the total but 0.9j 1d. So it shifts a day.

Problem 2
All activities are "as soon as possible"
Assigned the same person.
Activities 1 and 4 are 450 priorities, activities 2 and 3 priority 500
1) Why it shifts 4j Activity 4? (Milestone fixed without delay?)
2) Why Activity 4 is not done before the event 2?

Thanks
Attachments:

Please Log in or Create an account to join the conversation.

More
29 Jan 2013 22:36 #2 by babynus
Replied by babynus on topic Re: problem planning

Problem 1
I have 4 spots with such constraints: Regular between 2 date.
Each to the same resource
I calculate manually the delay to check the workload
My workload shift 1d ... It's strange? It does not calculate the total but 0.9j 1d. So it shifts a day.

It is just because of rounding. The work you assigned to task 4, distributed between dates, should be 4.3... So planning will round to 5 or 4. It should lead to the last day to 0.5 without having enough availability. So 0.1 must be planned the day after end date, visually shifting 1 day.
Can you check work planned for last day ?

Problem 2
All activities are "as soon as possible"
Assigned the same person.
Activities 1 and 4 are 450 priorities, activities 2 and 3 priority 500
1) Why it shifts 4j Activity 4? (Milestone fixed without delay?)

It should not.

2) Why Activity 4 is not done before the event 2?

It should not.
I don't see task 3 on second picture. Is it normal ?
Could you show detail of activities : assignement rate, priority, planning mode, cdependencies, ...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
30 Jan 2013 09:54 #3 by JCDe
Replied by JCDe on topic Re: problem planning
Hi,

I completed the document

Problem 1: Add the workload for 3 months. We see that shift 1.4 days because of rounding
Problem 2: I added a view of all activities + milestone. For dependencies we see on the GANTT view

Thanks

Please Log in or Create an account to join the conversation.

More
30 Jan 2013 22:19 - 30 Jan 2013 22:19 #4 by babynus
Replied by babynus on topic Re: problem planning
Hi,

Problem 1: Add the workload for 3 months. We see that shift 1.4 days because of rounding

The shift is "normal" (at least I dont' know how to avoid it).
It is becauses tasks 1, 2 and 3 are planned before.
So is does not leave enough availability of resource to finish before.
This is a very particuliar case : regular between dates for several tasks at once.
Maybe an improvement can be brought, to fill availability in the beginning of the defined period. But it should complexify planning calculation.
To be studied as a later improvement.
Ticket #976

Babynus
Administrator of ProjeQtOr web site
Last edit: 30 Jan 2013 22:19 by babynus.

Please Log in or Create an account to join the conversation.

More
30 Jan 2013 22:29 #5 by babynus
Replied by babynus on topic Re: problem planning

Problem 2: I added a view of all activities + milestone. For dependencies we see on the GANTT view

I recorded Ticket #977.
Are you sure there is no "delay" between milestone and task ? (check by editing dependency)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
31 Jan 2013 10:38 - 31 Jan 2013 10:39 #6 by JCDe
Replied by JCDe on topic Re: problem planning
Ok,

Problem 1:
What I do not understand is that during the month of February to early March there are activities 1, 2, 4 => There is the problem (total = 0.9 or 1).
Then from March 8 activities were 1, 3, 4 and he manages to complete the day (total = 1), very strange ....



For problem 2: Not delay :



I repeat the same data for problem 1 and 2, I only change the mode plannind "regular between 2 dates" => "As soon as possible"

Attachments:
Last edit: 31 Jan 2013 10:39 by JCDe.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.063 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.