Hi,
On your print screen, you don't dispayed the expected activity.
(the one with SATA in the name is expected)
But it gives me enough information to understand.
Your first activity, on 2013-2-27 is finished.
Your second activity, on 2023-2-28 is also finished
The "%SATA%" activity is started : apparently, 1/2 day is real work, on 2013-2-27, so you should have 1/2 day left.
Resource should have no availability left, so planning finished "%SATA%" activity on 2013-3-1 (as soon as possible).
This activity starts on 2013-2-27 (real work) and ends on 2013-3-1 (planned left work) : duration = 3 days !!!

What is not pointed out, is that there is no work on this task on 2013-2-28. You could see this is respource planning or work plan reports, on real work allocation for the resource...
Regards.