Hi Babynus,
2 questions actually:
1) I am facing a problem with the calculation of real work on a few activities: the parent activity does not take into account all the real work of its children activities (see "Parent_real_work_problem.jpg").
I believe this has happened after moving around some activities / projects. In order to investigate where this might have come from, could you tell me where in the source code is the real work calculated for a parent activity ?
My use case is this:
- in Real Work Allocation, log some time on a child activity, and save.
-> I have checked the saveImputation.php file, everything seems ok
-> I haven't found where the update of real work for the parent activity is done
2) While trying to figure this out, I played in the "demo" Projectorria, and now see something strange: I logged some small amounts of time on a child activity (66.5.2 test1), and when I check the Planning or Activity details, the real work on this activity is different! (see screenshots Activity, Planning, RWA).
These tests are done on the "MyOwnTestProject" of the demo site.
-> Any idea what could cause this ?
Thanks for your help!