the user choose a projet " X"
the sum the "assigned task" in the'resource planning' tab is different than in 'planning 'tab
i count the "assigned task" of all my resources and this quantity is different than the quantity that i can see in 'planning' tab
the reason is because in jsonResourcePlanning .php file in line 91, it is written
';$queryWhere.=' ass.plannedWork>0
the problemis the projet leader has fiiled out the activity
leftwork=0
ralwork=0;
assignedwork=2.5;
then we can't see this activity in resource Planing tab,
but i can see this activity in planning tab
perhaps, this issue can mislead the user,
i don' t know the runctional reason why the user can't see the activities bigger than 0 , in resource planning tab
Activity with left work = 0 is concidered as finished (no more work to do).
If left = 0 and real = 0, then activity has no planned work : planned = real + left.
Resouce planning displays the work to be done for a resource, so activities with no work done and no work left to be done are not displayed.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.