11 May 2014 10:41 #1 by hnoureldine
Hello,

How to force the planned start date to be calculed ? In fact, in my project I have a planned start date for a parent activity : 03/04/2014 while all validated start date are > 05/05/2014.

I calculated several times the planning via the button without succed.

The planned start date should be 05/05/2014



Thanks

Please Log in or Create an account to join the conversation.

More
11 May 2014 12:42 #2 by babynus
Replied by babynus on topic Planned start date
Do you have some work defined for your tasks ?
If not, what is the planning mode )
For defaut planning mode (as soon as possible) you need to have work defoined to get some result.
Otherwise, you need to change planning mode (fixed duration) to get things calculated

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
12 May 2014 14:16 #3 by hnoureldine
Replied by hnoureldine on topic Planned start date
hello,


it's solved now by affecting ressources to the parent activities.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.029 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.