13 May 2014 20:57 #7 by hnoureldine
Replied by hnoureldine on topic Jalon
The flag "done" is checked

Please Log in or Create an account to join the conversation.

More
13 May 2014 23:41 #8 by babynus
Replied by babynus on topic Jalon
Hi,

So the done date must be greater than validated end date.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
14 May 2014 21:12 #9 by hnoureldine
Replied by hnoureldine on topic Jalon
hi,

I put done date to 09/04/2014 but indicator still there

Please Log in or Create an account to join the conversation.

More
14 May 2014 21:13 #10 by hnoureldine
Replied by hnoureldine on topic Jalon
And the milestone is inred color now

Please Log in or Create an account to join the conversation.

More
15 May 2014 10:41 #11 by babynus
Replied by babynus on topic Jalon
Done date on 09/04/2014 sets Real End Date on 09/04/2014 which is after Validated End date (08/04/2014).
So indicator is still valid, and milestone must be red (validated end date not respected)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.