Hello,
I'm wondering if it is possible for the entire project timeline to shift to the left or right as appropriate when planned tasks are completed ahead of or behind schedule.
Thank you.
I am having difficulty having a follow on phase of a project shifting when a predecessor milestone is reached. Re-Calculating does not shift the project even though the milestone is 'done'. Am I missing a requirement? Please advise.
"Reach" of milestone is not enough : it could be late (delayed).
You must set it to "done".
Then real end date will be automatically set and planning will take it into account.
I have a three phase project ongoing with up to 30 dependent tasks (activities) per phase. I have the project built so that the phases have completion milestones as predecessors to follow on phases. Even though all activities and the completion milestone have been set as done, the follow on phases have not/will not shift (left) to the earliest available date for earliest project completion upon recalculating planning. What am I missing? Please advise.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.