16 Jun 2014 00:17 #1 by STRO
Hello,
I would like to know how to manage the following ressoiurce situation :
6 Peoples working on project. Usually no more than 2 on the same.
3 of them work alternatively 1 week on project and 1 week on helpdesk.
2 others work only 1 day per week on project, 4 other days on helpdesk.
The last one works only 4 days/week (0,8 ETP), 1 on project, 3 on helpdesk.
For instance, for the last ressource, I've set:
0,8 ETP on ressource,
I've created 3 projects :
Proj1: affectation 25% priority 500
Proj2: affectation 25% priority 100
Support (Admin project) 0,75 priority 10
Then I've created 3 tasks
Proj1Task1: Assigment 100% ASAP work 20 D
Proj2Task1: Assigment 100% ASAP work 10 D
Support2014: Assigment 100% regular between date work 143 D.
My goal is, like everyone ;) to be able to estimate the delivery date. However, with this set up I see no change on my planning after having add the Proj2Task1 and the Support2014 task. I don't see neither that my ressource is oveloaded.
Is this set up seems ok to you ? What would you recommend ?

Thanks for your help and thanks for this great job.
Stephane

Please Log in or Create an account to join the conversation.

More
16 Jun 2014 16:36 #2 by babynus
Affectations to
1 project : 25%
1 project : 75%
will lead to correct work for 1 day per week and 4 days per week.

Idem for 1 day per week and 3 days per week with resource at 80%.
Just be sure to set project with 1day per week with higher priority (smaller priority number), otherwise it will not be planned (fisrt would use the 4 available days)

Unfortunatelely, there is no way to plan 1 week on Proj1, 1 week on Proj2.
Best you can do is plan 50% each, and planning wil plan 2,5 days on each project each week.

I don't see neither that my ressource is oveloaded.

Resources will never be overloaded : target date will shift (it is ProjeQtOr planning design)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: STRO

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.