I try to setup a templete of 5 phases project (used in automotive business) and there are some milestones which depends on other (e.g. the last milestone should be 90 days after some other milestone). Is there a possiblity tho implement such a date? And how con I do this.
Thank you for your help.
Friedel
There is nothing good, except you do it. (Erich Kästner)
Yes, you can do this.
And you can do this in two different ways :
1) When creating the dependency between milestones, you can add a delay between them.
Just set the delay to 90 days and you'll get exactly what you want
2) Another way to do this is to add a "Fixed duration" task between the milestones.
Fixed duration to 90 days, with do what you expect, with first milestone predecessor of task and second successor of it.
It is a bit longer, but will allow to represent why there is a gap between milestones.
Just pay attention that ProjeQtOr always consider "Open" days.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.