[SOLVED] Closing Project with closed activites :

More
08 Oct 2014 14:12 #1 by DPo
Hi,
I try to close a project, but after closing all activities, tickets, milestone in the project, I just have a meeting left (any way to close a meeting ?)
, I still have a message disabling the closure of my project :

Invalid controls.
Unable to close an element with left work


Any way to know exactly where it blocks (activities, mailestone, ticket), the message is not explicit enough for me.

Thanks.

Please Log in or Create an account to join the conversation.

More
08 Oct 2014 14:18 #2 by protion
Hello

The problem probably comes from the fact that you stay a rest in one spot, the solution and put the rest to 0 in assignments
Bonjour

Le problème vient sans doute du fait qu'il vous restes un reste dans une tache, la solution et de mettre le reste à 0 dans les assignations
The following user(s) said Thank You: DPo

Please Log in or Create an account to join the conversation.

More
08 Oct 2014 14:20 #3 by DPo
That's it, I found that the time left on the meeting was not pointed out, so after bring it to 0, it closed ok !

Thanks.

Please Log in or Create an account to join the conversation.

More
08 Oct 2014 15:49 #4 by protion

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.056 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.