ProjeQtOr free project management software - How to plan a activity of several week but which will take place several times - ProjeQtOr
 

How to plan a activity of several week but which will take place several times

More
03 Oct 2015 14:35 #1 by licamale
Hi,
I use 4.5.5 version

How to plan a activity of several week but which will take place several times ?
For exemple in my projet i have a "Formation" activity with 15 days, i want to plan this activity during the weeks 12 to 16/10, 26 to 30 and 23 to 27/11. Weeks or days do not follow each other.
How i make in the proiject for use the schedule and use the function of calculation of the schedule of the activities ?

Thank's a lot for your answer

Please Log in or Create an account to join the conversation.

More
03 Oct 2015 15:27 #2 by babynus
In your exemple you just have 3 activities, that you can for instance plan as fixed duration.
You can if you please sum up these activities, just placing them under a top activity.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.