03 Nov 2015 19:46 #1 by fredparis
Hi,
Since few weeks, some activities status seems to be "blocked" :

1) when I create a new activity, after status "accepted", it's impossible to move to status "assigned"
=> a ressource is allocated, with same dates to the activity
=> in this status, I can allocate real work to the activity

2) when I want to stop an used activity (actually status "in progress"), it's impossible to move to "done".
=> I move the "rest to do" with 0 (no more work), and work percent is at 100% !!!

What are the constraints ? (if there are someone, of course...)
I think it was more easy before, with olders versions of ProjeQtOr.

Thanks for helping me... ;)
Fred

Please Log in or Create an account to join the conversation.

More
04 Nov 2015 20:22 #2 by babynus
There are no new constraints in V5.0 or V5.1 about status change.
Check your workflow : for the concerned activity, check the activity type, go to this activity type, check workflow, go to this workflow.
On the workflow, check which profile can change status from concerned status to expected status.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
06 Nov 2015 02:40 #3 by fredparis
Hi Babynus,
The activity type is "Task" and the workflow is "Default"
So, anybody can change a task from "accepted" to "assigned" or from "in progress" to "done".
But, for me, the status don't change.

Some precisions :
When I change the activty type in the activity window, I clck to the 'save buttun" to apply this new status to the activity.
The server is running (because the hourglass is waiting for a little bit long time (between 2 and 3 minutes).
After this step, a short message come with this text (approximative) : "Activity #130 changed" but the status don't change.

So I think that something is running correctly but not to have a correct result.
Any idea ?
Fred

Please Log in or Create an account to join the conversation.

More
06 Nov 2015 09:19 #4 by babynus
Could you please check log file (some errors are silent on user side) and browser console ?
Thanks.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
18 Jan 2016 17:01 #5 by fredparis
Hi, Babynus,

Happy New Year, and all my bests 2016 wishes for you, your family, your projects (and... "The" Project ! B) )

My problems are still remains here...
The Activity Status don't want to move after "accepted".
The "assigned" status isn't possible to affect... :S
I can work with this activities, and adding real work allocation.

I don't have modified anything into the basis workflow.

How (where ?) can I check the log file and the browser console ?
Thanks,
Fred

Please Log in or Create an account to join the conversation.

More
18 Jan 2016 23:23 #6 by babynus
Log file is by default on /files/logs/projeqtorYYYMMDD.log
Browser Console is displayed with [F12] on most browsers.

But I think your issue is more on the workflow definition.
Check possible changes and which profile can do the change.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.