You will not find difference between Assigned work and Real, because it is not an indicator on the project. How would you call that figure ?
You will find difference between Validated Work and Reassessed Work, it is called margin.
In fact I would like to know the difference between my forecast (Assigned work) and the Reassessed work (you're right it's not the Real Work.
My needs is to know if on a task or activity we will be ahead or late. The margin is a vision with the coast but I would like to have this vision in hours or days.
Ex :
John MacKleine has an assigned task of 5 days.
After 3 days of work, the Reassessed Work is 4 days.
We won 1 days theoretically at the end of 3rd day.
Then what you're looking for is margin.
Margin is calculated on days...
But what is compared is Reassessed (what you expect) and Validated (Baseline).
So you should just define validated work equal to assigned is order to have margin work the way you expect (in fact it should do the other way round : you define validated work, then assign resources on the task ...)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.