25 Aug 2011 03:10 #1 by Guest
'report' questions was created by Guest
Hi,

I have questions about the report page:

1. In planning-> detailed monthly activity planning, I specified the project, and generate the report, but it shows all the projects in the report.
Is that correct?

2. In some planning report, I see some cells are empty, some cells with real work hours, and some cells with planned work hours.
I'd like to know how 'planned work hours' are calculated.
And I see number '9.99' shown in the cells. When will '9.99' appear ?
Is that related to capacity (FTE) ? but why not integer.

3. In planning -> monthly availability of resource report, I see '0.0099999999999998' number in some cells. why will this number appear? what does it mean?
why not show '0' instead?

Please help.
Thanks a lot.

Best Regards,
Selina

Please Log in or Create an account to join the conversation.

More
25 Aug 2011 11:06 #2 by babynus
Replied by babynus on topic RE : 'report' questions

1. In planning-> detailed monthly activity planning, I specified the project, and generate the report, but it shows all the projects in the report.
Is that correct?

It's a bug => ticket #385

2. In some planning report, I see some cells are empty, some cells with real work hours, and some cells with planned work hours.
I'd like to know how 'planned work hours' are calculated.
And I see number '9.99' shown in the cells. When will '9.99' appear ?
Is that related to capacity (FTE) ? but why not integer.

Planned work is calculated when planning is calculated. The planned work is the repartition of left work taking into account activity constraints and resource availability constraints. Display of '9.99' is a rounding issue : work has been extended to number(5,2) while plannedWork is still displayed as (3,2) : so 10 is stored as nearest value (9.99) => Ticket # 396

3. In planning -> monthly availability of resource report, I see '0.0099999999999998' number in some cells. why will this number appear? what does it mean?
why not show '0' instead?

It's a consequence of previous bug : 10 - 9.99 has been estimated (in float value) to 0.009999999...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.