Report for function

More
21 Jan 2016 14:59 - 21 Jan 2016 16:09 #1 by igio80
Report for function was created by igio80
Hello, is it possible get a report for resource function in a project?
I would like get a report for:
  1. time total for project (I believe that planning is best output)
  2. resource type (Developer, Manager, ecc.)
  3. resource total hour planned

Then, if a resource is for example to 10% on a parent task that contains a lot of activities, how can I get total hour planned for that resource?

Thanks.
Last edit: 21 Jan 2016 16:09 by igio80.

Please Log in or Create an account to join the conversation.

More
21 Jan 2016 16:26 #2 by igio80
Replied by igio80 on topic Report for function
Is not possible?

Please Log in or Create an account to join the conversation.

More
22 Jan 2016 19:25 #3 by babynus
Replied by babynus on topic Report for function
1) an 3) "Monthly planning resource/project" should do the job
2) I don't understand the need

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
25 Jan 2016 09:20 #4 by igio80
Replied by igio80 on topic Report for function
Thanks, so "Monthly planning resource/project" is ok but I must set for each activity an Assignment resource with a number of day assigned otherwise I don't see planned day. Is it right?
I have created some activities where I set only a validated duration (so Gantt update automatically for each activity change duration) with one or more assignment (with set only rate to 100%).
Point 2 (resource type (Developer, Manager, ecc.)) I mean that I add a "Functions" called "DBA" in "Lists of values". I would like assignment a resource for some activities with this function and I need of a report to estimate how time "DBA" is engaged on my project.
I hope I have been clear.
Thanks a lot.

Please Log in or Create an account to join the conversation.

More
25 Jan 2016 10:01 #5 by babynus
Replied by babynus on topic Report for function

Thanks, so "Monthly planning resource/project" is ok but I must set for each activity an Assignment resource with a number of day assigned otherwise I don't see planned day. Is it right?

Yes.
ProjeQtOr is work driven.
You must define work (who works on which activity/task for how many days) to get a planning.

I have created some activities where I set only a validated duration (so Gantt update automatically for each activity change duration) with one or more assignment (with set only rate to 100%).

If you want a fixed duration, you need to set "planning mode" = "fixed duration", otherwise your validated duration is only informative when you set some assignments.

I mean that I add a "Functions" called "DBA" in "Lists of values". I would like assignment a resource for some activities with this function and I need of a report to estimate how time "DBA" is engaged on my project.

There is no report to get this. You'll have to build your own (or request for a quote if you want to have it built for you)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.