Hello,
The margin is calculated regard to the cost or day validated and the cost or day reassessed (if I well understood).
So I at the beginning of a project you have to validated a load in days.
For instance:
-if I have a project validated with 100 days at the starting,
- at the middle of the project I have spent 60 days (instead of 50),
- I make a reassessment because the project shift, and the remaining load is not 40 days but now 50 days,
- So my new margin in days is now -10 days.
When you are manager you can access to the menu “work/activities/assignment/left” and modify “left work” (which is by default equal to 40 days regard to my example) and set it at 50 days to put in evidence the shift in load of 10 days.
Is it the only way to put in evidence the shift? And when you are a simple user how can you modify the “left work” as users have not access to the menu “work/activities/assignment/left”.
Thank by advance for any precision.
Eric
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.