I have created a projet with only one resource on one year. The planned days = assigned days = reassessed days = 212. The resource a real work allocation of 25 days and no shift is identified on the planning. However in report “planning work plan by month” the sum of days is 215 instead of 212 (see attached copy display, surrounded in red) ?
Thank by advance for any explanation
Eric
On february, you have real work and planned work.
I guess that real work was not entered exactly as planned (this is real life).
So you need to replan the project in order to actualize planned work on february.
Then report should be correct.
Thank you I understand the calculation. In fact you have to recalculate the activities planning in the planning menu to have the right figure.
But I have a comment regarding to the “work plan per month” menu, the data underlined in yellow should not be identified as “planned” data but rather as “reassessed” data as they are in conformance with reassessed data and not planned data once you recalculate the activities planning.
Eric
I have underline in same color (see display copy attached) the data that are consistent between project and planning. What is called “planned” in planning is in fact left days regard to the project data. That may be a little confusing as planned may be understood as initial charge in days.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.