Action Managment - copy of linked elements

More
04 Mar 2016 12:43 #7 by psc
Thank you and sorry if this is annoying,
trying to re-think my idea of managing corrective action plans.
What I really need to do is follow up corrective actions through the following steps that might be assigned to different people:
Keeping track of working time on these would be nice.
1) Stock isolation (e.g. assigned to production manager or quality manager if stock at customers)
2) Root cause analysis (R&D project manager or process responsible or group)
3) Application of solution (impacted process responsible or group)
4) Verification of solution (test operator or process responsible)
5) Validation of solution (director or customer or other)

How would you do that in ProjeQtOr?

Please Log in or Create an account to join the conversation.

More
04 Mar 2016 23:28 #8 by babynus
Just define a workflow, with restriction of profil able to change from one status to another.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: psc

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.