Change Week Ends

More
29 Feb 2016 12:43 #1 by mohamedabdelwahed
Hello , Is there is any way to change the week Ends from Sat and Sun to Fri and Sat

Please Log in or Create an account to join the conversation.

More
29 Feb 2016 13:51 #2 by babynus
Replied by babynus on topic Change Week Ends
It is a planned evolution to define off days.
Today, only possibility is to go to default calendar, click every friday (to indicate it as closed) and every sunday (to indicate it as open). I bit laborious, but not so long (less than 10mn).

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: mohamedabdelwahed

Please Log in or Create an account to join the conversation.

More
18 Nov 2018 09:56 #3 by mohamedabdelwahed
Replied by mohamedabdelwahed on topic Change Week Ends
Hello , Did this change happened or not yet .
Regards

Please Log in or Create an account to join the conversation.

More
18 Nov 2018 10:23 #4 by babynus
Replied by babynus on topic Change Week Ends
Yes, since several versions... (I don't remind which but at least since 7.0)
In global parameters you can define for every week day if it is Worked or Off duty.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.