I have exported from one Projeqtor instance some activities as CSV and want to import them now to another instance (version 5.2.4). For several fields (creation date, validated start date, ..) I get the above error message.
In the CSV file this dates are in the format
...;15.01.2016;...
When I imported some projects in the same way (and with an identical format) I have had no problems.
What is the valid date format and why does it differ between projects and activities?
Date format do not differ from Projet and Activities.
What I guess is that you opened your file with Excel to edit it and saved from Excell : it is Excell that changes date formats.
Expected format is YYYY-MM-DD : international format, with no ambiguity about day and month and supporting sorting.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.