I'm facing a problem. When I assign a resource to activity and want to set hours of assigned work, I will get error at some situations.
If the quantity of hours is less 10,000 hours, it will be good.
But if this quantity is equal or more than 10,000h, I will get error.
Can I change this limit? If yes, how?
Thanks.
Attachments:
Last edit: 21 Mar 2016 11:24 by DEngine. Reason: error
This is a restriction that will be changed on V5.3.
Possible values should go up tp 9,999,999.99
If you need to enter assignment or 10,000 hours, you can enter 2 assignments of 5,000 hours for same resource (yes, it's possible )
NB : IMO 10,000 hours (more than 1,000 days) for same assignment if much too important.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.