How to display "Activity" in "Diary" ?

More
05 Apr 2016 20:00 #7 by william.senez
Yes the problem is the same !
No task in the diary ! (Just ticket is display, no task !)
I dont find why !
Attachments:

Please Log in or Create an account to join the conversation.

More
05 Apr 2016 20:04 #8 by william.senez
Yes the problem is the same ! (see attachements)
No task in the diary ! (just ticket)
I dont find why I can't see all task in diary !
Can you help me ?
Best regard.
Attachments:

Please Log in or Create an account to join the conversation.

More
05 Apr 2016 20:12 #9 by richard.pare
Can you show me the calendar on April 18 2016?

Planned activity date (April 18 2016)

Please Log in or Create an account to join the conversation.

More
05 Apr 2016 21:50 #10 by william.senez
I find the problem !
0 day affected to the ressource for task !
Now the task is display on diary !
This is the solution ?

I like this nice software !

Thx best regard !

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.