Show "extra" days in projects

More
21 Apr 2016 18:49 #1 by IgaBiva
Hi all,
noob question I guess, but so far I cannot see when a project is delayed in planning view :blush: .
Do progress bar can switch from green to red when end date has passed ? (green before end date and red after)
So I can see right away how many days I underestimated ???

Thanks !

Please Log in or Create an account to join the conversation.

More
22 Apr 2016 22:07 #2 by babynus

Do progress bar can switch from green to red when end date has passed ?

Yes : define target end date in Validated end date. If planned end date passes over Validated end date, task is red.

So I can see right away how many days I underestimated ???

Define validated cost. Then margin will indicate difference between validated and reassessed work. Negative margin is underestimated work, and so displayed in red.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.028 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.