Hi all,
noob question I guess, but so far I cannot see when a project is delayed in planning view .
Do progress bar can switch from green to red when end date has passed ? (green before end date and red after)
So I can see right away how many days I underestimated ???
Do progress bar can switch from green to red when end date has passed ?
Yes : define target end date in Validated end date. If planned end date passes over Validated end date, task is red.
So I can see right away how many days I underestimated ???
Define validated cost. Then margin will indicate difference between validated and reassessed work. Negative margin is underestimated work, and so displayed in red.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.