View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Overall progress? - ProjeQtOr
 
 

[SOLVED] Overall progress?

More
25 Apr 2016 17:08 - 25 Apr 2016 17:09 #1 by pavilonsxx
Overall progress? was created by pavilonsxx
Hi all,
I have some questions for help
1. Overall progress is entered manually or automatically, when creating projects, to select how value is reasonable? Thanks to explain in more detail.
2. If there is activity ahead of schedule, projeqtor will show how? For example, user A responsible activity X, is assigned 3 date but actually only 2 date the user A has completed the activity, so how does the user A to enter into real work allocation?
Thanks for help!
Last edit: 25 Apr 2016 17:09 by pavilonsxx.

Please Log in or Create an account to join the conversation.

More
25 Apr 2016 20:02 #2 by richard.pare
Replied by richard.pare on topic Overall progress?

Overall progress is entered manually or automatically, when creating projects, to select how value is reasonable?


Manually!
Set directly on Project screen (See field: Overall progress).
You can modify the list of values via "Overall Progress" screen.

If there is activity ahead of schedule, projeqtor will show how?


In Resource planning Gantt chart.


A has completed the activity, so how does the user A to enter into real work allocation?


Just need to set 0 to in left work column.
Also you can enable 'automatic status change'
This allows to change the status of tasks to done.

Attachments:
The following user(s) said Thank You: babynus, pavilonsxx

Please Log in or Create an account to join the conversation.

More
28 Apr 2016 16:52 - 28 Apr 2016 16:52 #3 by pavilonsxx
Replied by pavilonsxx on topic Overall progress?
No more left work, but the task status will not change because at issue is occurring
I do not understand. Can explain in more detail?
I'm sorry, I'm just an amateur
Thanks for the help
Last edit: 28 Apr 2016 16:52 by pavilonsxx.

Please Log in or Create an account to join the conversation.

More
28 Apr 2016 17:12 #4 by richard.pare
Replied by richard.pare on topic Overall progress?

No more left work, but the task status will not change because at issue is occurring
I do not understand. Can explain in more detail?


Check your activity type.
If the activity type require a responsible or a result.
The activity status can't change automatically.
In this case, the responsibility must set the status to 'done' manually.
The following user(s) said Thank You: pavilonsxx

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.050 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.