ProjeQtOr free project management software - Wrong manipulation with plannification ? - ProjeQtOr
 
 

Wrong manipulation with plannification ?

More
25 May 2016 15:33 #1 by Jonathan02500
Hello all ,
I have a question concerning plannification.
I want to start my project tomorrow,
So i put into my requested date the date of tomorrow but each time the software chnange the planned date at today.
I don't know why, someone can help me please ?

Have a good day.

Please Log in or Create an account to join the conversation.

More
26 May 2016 08:31 #2 by babynus
The requested date is just informative : the date the customer requested (his Christmas wish list)
The date that should be taken into account is the validated start date. But it is not a constraint to planning calculation.
You need to set a real constraint to planning calculation. For instance, add a "fixed" milestone starting on tomorrow, then make your first task of project start after the milstone (add dependencing link).

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
26 May 2016 09:53 - 26 May 2016 12:07 #3 by Jonathan02500
Hello
Thank you for you reply, i understand a little more now :)

When i want to plannify my ressource i don't understand but when i put 5 days on my "charge" (#1 in my screenshoot) and i modify the assignation of the ressource and fill 5 days (#2 in my screenshoot) the planning is modify and as you can see (#3 in my screenshoot) there is 7 days of work, howerver i want 5 ?
Can you help me please :)

And can you tell how the value in yellow is calculate please in my second screenshoot.

Have a good day :)
Attachments:
Last edit: 26 May 2016 12:07 by Jonathan02500.

Please Log in or Create an account to join the conversation.

More
26 May 2016 19:42 #4 by babynus
Have a look at report "planning per resource/project/activity" in "planning" report category.
You'll see exacly what the resource does or is planned to do on the oeriod.
Maybe he is busy on another project.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
27 May 2016 09:34 - 27 May 2016 14:50 #5 by Jonathan02500
Hello,Thank for your reply,
Thanks to you i learn a lot of things about the software.

However my problem isn't solve yet.
As you can see in attachment my ressource isn't use in other project so i don't know why the capacity is 6days :'(

Have a good day
Attachments:
Last edit: 27 May 2016 14:50 by Jonathan02500.

Please Log in or Create an account to join the conversation.

More
30 May 2016 21:40 #6 by babynus
Your resource is attending a meeting, on friday, taking 0,06 days of resource availability.
So this resouce cannot work 5 full days on the task you expect him to work. The 5 work days (as workload) will be planned in more that 5 dayxs (exactly 5,06 days, being reported as 6 day (duration is not rounded but ceilled)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.