Is there any way, on the planning screen, when it's filtered, to see Milestones from the projects above?
The problem is, the Milestone counter and the Project counter is the same for WBS calculation.
If I create a milestone in project 1.2, this milestone WBS will be 1.2.X and I won't be able to see it in others sub projects (1.2.Y) on the planning screen.
So my question is : Is there a way to have "inheritance" for milestones from the main project to the sub-projects.
No, there is no way, and it's not planned to design such feature.
Only way in your case is to display project 1.2, and you can "shrink" sub-projects you don't want to see.
Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: chenevieredd
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.