11 Jun 2016 19:37 #1 by Jonathan02500
I'm using your software since 3 weeks but i don't understand the difference between each date when i create a project or an activity.
What is the difference betwen :
Valided
Planned
Real
Requested.

Thank you very much and have a good day :)

Please Log in or Create an account to join the conversation.

More
11 Jun 2016 20:09 #2 by babynus
Requested = the first request from your customer (his Christmas wish list)
Validated = what you finaly committed with your customer. It is your baseline.
Planned = calculated by PrjeQtOr taking into account work assigned to resources, resources availability and all the constraints on tasks and resoures.
Real = defined from real work allocation (real start date = first date for real work)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
12 Jun 2016 10:57 #3 by Jonathan02500
Thank you very i understand now :)
Have a good day. :)

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.