On one of our project, I'm getting quite a strange comportement in real work count :
The meeting has been correctly created, assignment too, and real work entered for every resource. However, as you can see, the total real work is not equal to 0.5d but only 0.125d. Then the meeting can't be closed as there is still assigned work not consumed.
One other strange thing is that on the real work input table, the start date and end dates are not coherent (the meeting took place today 14 of June) :
However, I don't think the meeting has been badly defined :
Do you have any idea of what can be wrong and how to fix it ?
Very weird indeed.
Could you show print screen of real work allocation for each resource on meeting date ?
Could you also post extract of table "work" ?
For information, to close the meeting you can manually update left work to zero.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.