Hi,
To begin, thank for your training.
I try to create my recurent users support activity. I think this activity take 20% of my time.
Do i have to estimate the annual charge for this ?
so to do that i take this calculation :
18 day of wrok by month * 12 = 216
20% of 216 = 43 days dedicated for users support
In a project named "recurrent" i had créate an activity with validated start date from 01/01/2016 to validated end date 31/12/2016.
I assignated this task to me and charge with 43 days of work and setup this tasks planification to "regular betwin 2 date".
It 's the right approach ?
Can't i simply setup anywhere -> this activity take 20% of my global time or charge without having to make the charging days estimation calculation on the year ?
Can't i simply setup anywhere -> this activity take 20% of my global time or charge without having to make the charging days estimation calculation on the year ?
No, as of today, there is not way to "calculate" a workload from other inputs.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.