I currently use the report "Planning > monthly planning resource/project/activity" to follow my daily activities.
But planned work are added to real work.
So the sum of each day and each activity is not good.
Is it possible to hide planned work to see only real work in reports ?
And in the future, having an option like in the "real work allocation" screen, with the "show planned work" check box ?
Or is it possible to have a new report in "real work" section, like the monthly planning, with only real work of each day.
Because (and I'm shure I'm not the only one) I need to report my activities each month to my office.
So, this is a very useful report.
Hi,
Perhaps I found the reason why.
In the Planning screen, after a clic on "Calculate activities planning" then planned work disapear on past days (but non on future days).
Is it the good way to proceed ?
Thanks for your help,
Fred
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.