I am on a mission to a client for 2 years.
I have 5 projects to manage :
How to divide the planning ?
- each project has the same start and end dates (the dates of the mission)
- which type of planning : as soon as possible? fixed duration ?
- resource (me) : 50%, 10%, 10%, 15%, 15% (estimation of each duration) ?
- project: duration of the mission x 50% (example for the first project)?
- or each project duration = 100% of the mission and the percentage of the resource will do the calculation ?
Then, I think it's the same method to be used with activites into each projects
Thanks for this little help.
Fred
All depends how you will execute the project.
If they are "recurrent" projects, the best is possibly to use fixed between dates planning. Then you just indicate planned work for each task, and planning will reguliarly plan work from start to end...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.