19 Aug 2016 19:36 #1 by fredparis
Planning method was created by fredparis
Hi Babynus,

I am on a mission to a client for 2 years.
I have 5 projects to manage :

How to divide the planning ?
- each project has the same start and end dates (the dates of the mission)
- which type of planning : as soon as possible? fixed duration ?
- resource (me) : 50%, 10%, 10%, 15%, 15% (estimation of each duration) ?
- project: duration of the mission x 50% (example for the first project)?
- or each project duration = 100% of the mission and the percentage of the resource will do the calculation ?

Then, I think it's the same method to be used with activites into each projects
Thanks for this little help.
Fred

Please Log in or Create an account to join the conversation.

More
21 Aug 2016 23:28 #2 by babynus
Replied by babynus on topic Planning method
All depends how you will execute the project.
If they are "recurrent" projects, the best is possibly to use fixed between dates planning. Then you just indicate planned work for each task, and planning will reguliarly plan work from start to end...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.027 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.