No, Christophe Noisette has a 200% rate. I put a such rate because I want that for some project, the working day is more than a normal working day. I did it so to manage "over time work".
It won't change a thing compared to 100%.
Allocation rate is not a capacity, it is just a limit...
No, Christophe Noisette has a 200% rate. I put a such rate because I want that for some project, the working day is more than a normal working day. I did it so to manage "over time work".
It won't change a thing compared to 100%.
Allocation rate is not a capacity, it is just a limit...
OK I put back 100% ... but I have still an alert saying that "Following tasks could not be completely planned :
7,4 h - Christophe Noisette - Meeting #56 : CA"... so the pb is not here...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.