ProjeQtOr free project management software - Dates planifiées largement postérieures aux dates validées - Page 2 - ProjeQtOr
 

Dates planifiées largement postérieures aux dates validées

More
04 Jan 2017 16:39 #7 by MFellow
Hello,
The allocation rates of the different resources were initialy based on the ratio [planned work / working days during the global period of the project]. The allocation rates were therefore fairly low.
In my example, the work of one resource was planned so that it could only work 0,4 a day and one day a week because of its very weak allocation rate. That's why the final date was planned so far in the future. In this particular case, an additional working day cause the final date to be planned a week later approximately.

Thank you for having pointed the affectation of the resource to the project. I could not access this information three days ago because I had only a "crew member" profile in the project. This has been freshly modified.
Best wishes for the new year.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.046 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.