It is because Activity has no assigned work.Exemple 1
I don't understand why my activity is planned to start the 02/02 and not the 01/02 ? A milestone don't have any durantion also my activity should be start the 01/02, isn'it ?
You mismatch Duration and Work.Exemple 2
For me, it is not the reality : I have to work 1 day but distributed on a duration of 3 days : how is it possible to have this graphical representation ?
Please Log in or Create an account to join the conversation.
babynus wrote:
It is because Activity has no assigned work.Exemple 1
I don't understand why my activity is planned to start the 02/02 and not the 01/02 ? A milestone don't have any durantion also my activity should be start the 01/02, isn'it ?
Add some assigne work and activity will start on correct date (ProjeQtOr is effort driven)dnaton wrote:
Sorry but why this method ? with or without assigned work, milestone don't have any duration, no ?
First, when I create a project (but maybe is it only me), I enter only duration and dependancies betwenn activities, to have an idea of the global duration of my project. After, I enter assigned work.
I understand it is how works Projeqtor today, but is it difficult or possible in the future to start an activity the same day as the milestone ?babynus wrote:
You mismatch Duration and Work.Exemple 2
For me, it is not the reality : I have to work 1 day but distributed on a duration of 3 days : how is it possible to have this graphical representation ?
With planning mode ASAP, work will be planned ASAP...
What you expect is done with plannong mode "fixed duration"dnaton wrote:
I'm not sure to mismatche duration and work : an activity can have a duration of 5 days for example, but with only 1 day work : this 1 day work is distributed all the 5 days duration. As Project Manager, I know that my activity is planned for 5 days (for different reasons) but has only a work of 1 day.
Actually, if I use "Fixed duration", I keep the right duration if I assign 1 day work, but I can't also no more fix a start date without the lost of the right duration.
And If I use the "ASAP constraint", I lost the duration if I assign a work (the same if I use "no start before this date" constraint
Please Log in or Create an account to join the conversation.
We'll see what can be done.understand it is how works Projeqtor today, but is it difficult or possible in the future to start an activity the same day as the milestone ?
If you want some "floating" task, you set planning mode as "fixed duration" and add predecessor.Actually, if I use "Fixed duration", I keep the right duration if I assign 1 day work, but I can't also no more fix a start date without the lost of the right duration.
Please Log in or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.