Team assignment to a task

More
27 Feb 2017 10:30 #1 by seb1981
Hi,

Is there any solution to facilitate task assignment ?

we can affect an entire team to a project but after that, we need to add the entire team manually to the task, one member at a time.

Can we assign team to a task or maybe copy all assignment of an other task to the current ?

Have a nice day

Seb

Please Log in or Create an account to join the conversation.

More
28 Feb 2017 14:58 #2 by babynus
Replied by babynus on topic Team assignment to a task
No, it's not possible as it is a very specific use case.
In most cases you will assing 1 ou 2 members of the team, not all.
Only known exception : meetings (team meeting for instance) : and it's possible to assign whole team to a meeting.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.