i created a project with some activities . Now when i go to the project, the PLANNED END DATE is giving me dates i did not put .The crazy thing is i cant change the dates.My starting dates are good, my end dates are good. The only problem is the PLANNED END DATE that i would like to change please. In the Attacment you will see the date 26/08/2044. Merci.
Planned dates are calculated from Work assigned, taking into account all the constraints (resource capacity, planning mode, priorities, dependencies, ...)
Hi,
I got same issue . They are two hours at list I'm trying to understand where the planned date has born in order to change it . No way until now.
I checked all Projects. Activities, Resource, Users ...
The solution is really nice but it's too complex to understand in all its behaviors .
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.