I am new to Projeqtor; Have been assigned to verify and setup Projeqtor as per team requirements.
Requirement is that workflow should automatically move to next stage i.e.: From Recorded to In Progress if a specific activity is completed or a milestone is achieved.
You can define your own workflows, but you'll have to manually change stauts (most of the case)
You can use few automations linked to real work allocation.
=> activity is moved to "in progress" when first real work in entered
=> activity is moved to "done" when no more left work exists
You'll find corresponding parameters in global parameters screen, in section "real work allocation"
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.