I want to manage dependancies between 2 projects led by 2 differents teams.
If I link a task on the first projet (supplier) to a fixed milestone on the second project (customer), it works well, as I expect it to do. The milestone is displayed in green or red as the constraint on the fixed date is respected or not.
My question is how to do this between 2 milestones?
I'm aiming to do so:
Project 1 (supplier)
Milestone A (floating milestone) : delivery of XXX
Project 2 (customer)
Milestone B (fixed milestone) : supplying of XXX by project 1, Milestone B is linked to Milestone A
Unfortunately, it seems not working, milestone B is always green.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.