Hej!
I have a planning issue. I want to assign different users to the same task to do something at the same time.
As example a training.
10 group members has to follow a training of 1 day. I want to assign all these people to that task because I want to calculate the project cost. If I just assign them, the planned duration will be 10 days. But it will be 1 day with 10 recourses with the same task.
If you assign 10 resources, 1 day each, duration will not systematically be 10 days, it can be more or less, each resource being planned at different date.
You can simply use planning mode "work together". This will force to find a day where every resource is available.
Or, if you know the day (for a training course it seems valid) just use a meeting !
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.