22 Jun 2017 13:58 #1 by hugi
Hej!
I have a planning issue. I want to assign different users to the same task to do something at the same time.

As example a training.
10 group members has to follow a training of 1 day. I want to assign all these people to that task because I want to calculate the project cost. If I just assign them, the planned duration will be 10 days. But it will be 1 day with 10 recourses with the same task.

How can I do this?

Please Log in or Create an account to join the conversation.

More
22 Jun 2017 14:13 #2 by babynus
If you assign 10 resources, 1 day each, duration will not systematically be 10 days, it can be more or less, each resource being planned at different date.
You can simply use planning mode "work together". This will force to find a day where every resource is available.

Or, if you know the day (for a training course it seems valid) just use a meeting !

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: hugi

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.